Election issue. Mayor Hazel McCallion recently answered questions in front of television news cameras at the construction site for the 280-megawatt power plant on Loreland Ave., near the Mississauga/Etobicoke border. The Mayor said the City had opposed the plant since 2004 but had to finally issue a building permit because of a ruling by the Ontario Municipal Board in favour of Ontario Power Authority. Now, only the Ontario government can stop the project. Here, Coalition of Homeowners for Intelligent Power (CHIP) member Stephen Thompson confronts the Mayor after the TV interview. Staff photo by Fred Loek
为了所谓的"绿色能源计划", 自由党省府听任开发商在QEW/427附近建天然气发电厂, 还在一个多月前欺骗老百姓说有什么"二次审核", 现在人家都动工了, 自由党的"二次审核"哪里去了?
法官 发表于 2011-7-25 13:47
这个东部电力有限公司不就是说在密市市区建天然气发电厂是安省绿色能源计划的一部分, 于是自由党省府就不管当地居民的抗议啦空气污染啦等情况动工开建! 其实在人口密集地区建设大的天然气发电厂本身就是有损大量居民健康的事, 比偏远地区的燃煤发电厂对安省居民的威胁更大。 |
|